September 26, 2003
Fourth Delivery of Phase III Equipment
A A A 缩小 加大 更大

On 27 September 2003, YICT received two quay cranes and five Rubber-Tyred Gantry Cranes (RTGCs) following the third delivery of equipment on 17 September. To date, a total of 27 RTGCs and five quay cranes have arrived at YICT. According to schedule, three more deliveries will be made this year in preparation for the second berth of Phase III at the end of the year.

The first berth of Phase III has now entered its final stage, and all operational facilities, equipment, operators and computer control systems are ready for operation.